Skip to main content

Final two towers in place for new gondola at Mt Ruapehu

Published by
Mountain Technology,


The New Zealand Herald is reporting that the final two of 14 towers forming the base of the pathway for Mt Ruapehu's new high-speed Sky Waka gondola, manufactured by LEITNER ropeways, are now in place.

Ruapehu Alpine Lifts said both towers 11 and 7 were a challenge to install, as they were in difficult-to-access locations with little access to power and machinery. The former was also in a geologically complex site.

Whakapapa general manager, Jono Dean, said: "The challenge here was excavating a large enough hole for the concrete footing [for tower 7] and it was complicated by the fact that we could only use a small excavator.

"On top of this we needed to bag all of the excavated material and lift it out with the material ropeway, and store it safely until the footing was ready to be back filled. It's essentially been a hand-dug excavation."

Referring to tower 11, Dean said: "It's located in a small outcropping on a location we call '2nd Waterfall'. The rock is solid lava so there was no possibility of excavating a traditional footing here. In addition to this we have no way to get an excavator to this site so all the drilling had to be done with handheld units.

"Four large anchor bolts were set into the rock, glued into place and then once set, pull tested to ensure they were sufficiently strong for the foundation to be anchored to. The tower itself is the tallest on the whole lift at 22 m," he said.

Next the haul rope for the gondola will be installed. Pilot lines, which are smaller in diameter, are already in place and these will be used to pull the main haul rope up and then back down the other side of the lift ready to be spliced together.

The spool containing the haul rope weighs approximately 48 000 kg.

Dean said the LEITNER ropeways team had faced a number of challenges along the way with the gondola project but had overcome them all very efficiently and kept construction progressing as quickly as possible.

"Delays are expected working in an ever changing mountain environment and due to this the opening date for the Sky Waka has moved out a little from the beginning of June to the end.

The Sky Waka features fifty Sky Waka gondola cabins with floor to ceiling glass for views, internal ski racks, audio and lighting and individual leather seats.

The gondola will run from the top of the Bruce base area directly to the Knoll Ridge Café, and will transport 2400 people per hour over the 1.8 km in approximately five minutes.

As a public benefit entity Ruapehu Alpine Lifts invests its proceeds back into developing the mountain's facilities and the new gondola forms part of the NZ$100 million reinvestment strategy announced by the Ruapehu Alpine Lifts board in 2015.

Read the article online at: https://www.mountaintechnologymagazine.com/ski-lifts/21052019/final-two-towers-in-place-for-new-gondola-at-mt-ruapehu/

You might also like

 
 

Embed article link: (copy the HTML code below):


 

Mountain Technology is not responsible for the content of external internet sites.